Pfizer 3C BZA CE
Leo Lynch delivered engineering solutions for a major secondary pharmaceutical plant expansion on a “live” process facility, including scheduled shutdowns to minimise impact on production and operations.
- ClientPfizer
- Main ContractorSISK
- EngineeringFluor
- QSWyeth Direct
Project details
A large-scale and complex project, delivered in a live process facility.
This project for Pfizer Newbridge (formerly Wyeth Medical) was a major secondary pharmaceutical plant expansion on a live process facility.
The facility included HVAC, process and Sprinkler Installations, a two-storey office and conference facility to accommodate 200+ personnel, five communication rooms serving full production and product cold storeroom facilities. The system consists of full AC with constant volume with re-heats.
Leo Lynch took an active role in the overall design process from an early stage through early contractor involvement. The team developed the P&IDs, GAs, specifications and detailed designs including ISOs. This project was designed in 3D.
List of services delivered:
- Process
- Mechanical
- Lift & Shift
- Off site manufacturing
List of utilities delivered:
- Clean steam
- Clear air
- Process water
- Purified water
- Contained waste
- Double contained waste system
- Steam & Condensate
- Chilled water
- Cooling tower water
- LPHW Steam & Condensate, 200°C